Control charts for variables are based on data derived from:

  1. Averages of small samples

  2. Total population measurements

  3. Individual measurements only

  4. Estimated values from historical data

The correct answer is: Averages of small samples

Control charts for variables are primarily constructed using data derived from averages of small samples. This method allows for monitoring the performance of a process over time and managing its variability. By utilizing averages, the control chart can effectively smooth out random fluctuations that may occur in individual measurements, providing a clearer picture of the process stability and trends. Additionally, averages of samples are instrumental in determining the process capability and the overall quality control metrics. This is particularly important in statistical process control, where a frequent analysis of sample data aids in identifying when a process may be going out of control, prompting timely interventions. In this context, using averages rather than total population measurements or individual measurements helps to mitigate the effects of variability, ensuring that the control chart is responsive to genuine shifts in process behavior while minimizing the noise introduced by random fluctuations. Therefore, structuring control charts around averages of small samples is an essential practice in managing quality control effectively.